Overview

As populations grow denser and climate patterns bring more intense rainfall, sewer infrastructure can struggle to keep pace with sudden surges in volume. According to estimates by the U.S. Environmental Protection Agency (EPA), approximately 850 billion gallons of untreated wastewater and stormwater are released into U.S. rivers, lakes and coastal areas each year. Just as we wouldn’t tolerate plumbing backups in our own homes, we shouldn’t accept sewage overflows in our cities.

Underground wastewater equalization (EQ) containment tanks are a critical asset in modern municipal and industrial infrastructure because they help prevent excess wastewater from overwhelming our treatment plants and forcing untreated water directly into local rivers and neighborhoods.

As a proven civil engineering design tool, solutions utilizing large subsurface storage tanks can provide several benefits:

  • Help cities manage wet-weather flow equalization at treatment plants.
  • Control sanitary and combined sewer overflows (SSOs/CSOs) from being released into the environment.
  • Provide containment of polluted runoff from industrial, airport deicing, firefighting foam and other harmful discharges.

Because these tanks store large volumes of chemically aggressive and environmentally hazardous fluids, their design requires attention to several aspects, including structural capacity, corrosion resistance, service life, and straightforward inspection and maintenance. These design parameters also must be balanced with other considerations such as site constraints and project budget to provide a safe, resilient and cost-effective wastewater containment tank.

The following provides a general overview of some of the preliminary design considerations for large-volume wastewater containment tanks to help municipalities and owners develop a successful design strategy, avoid environmental fines and mitigate public health issues.

Tank Sizing

Wastewater storage volume depends on a variety of factors, including local rainfall intensity, watershed area and population size. For smaller communities, localized CSO/SSO storage may range from 20,000 to 500,000 gallons, whereas a medium to large city may include multiple watershed areas, each requiring 1 million to several million gallons of storage.

Determining the peak-flow storage volume (or equalization volume) requires a comparison of the cumulative volume difference between the incoming wet-weather flow hydrograph and the maximum allowable outflow rate routed to the downstream treatment plant. The tank should have enough volume to contain the maximum expected excess flow surge for a given area and rain event.

Site Location

For areas with space constraints, high land values or zoning codes, municipal SSO and CSO systems may be installed underground, allowing the surface on top to be used for parking lots, parks or other facilities. Buried structures such as large-diameter pipe arrays or concrete vaults can offer some advantages over above-ground alternatives:

  • Can allow for peak wet-weather flows to enter and drain from the storage system without requiring immediate heavy pumping.
  • Provides protection from high winds, hurricanes, tornadoes and extreme temperature fluctuations.
  • Creates usable space on the surface for parking lots, access roads, parks and landscaped areas.
  • Improves aesthetics and prevents negative visual impacts in residential or high-traffic commercial areas.

Optimally, the storage system should be located in an area that allows an efficient connection to the existing interceptor trunkline and can utilize gravity flow to minimize the need for an additional lift station.

An “inline” design configuration places the storage system directly in series with the main flow path, and all incoming wastewater flows straight through the storage vessel under normal conditions. This provides for a simple design layout with fewer diversions but allows the entire volume of flow to mix through the tank during heavy surges, which can stir up settled solids.

An “offline” design configuration typically is stationed parallel to the main flow path, and a flow-control device (such as a high-level side weir) is used to prevent effluent from entering the storage tank until the trunkline reaches a set capacity or trigger level. After the rain event has passed, effluent can be routed back to the wastewater treatment plant during off-peak or low-flow hours.

Tank Material

Large-volume subsurface containment tanks are traditionally evaluated as a concrete storage vault or a large-diameter pipe-array system such as steel-reinforced polyethylene (SRPE), high-density polyethylene (HDPE) or fiberglass. These solutions offer the ability to contain a significant amount of wastewater in a relatively localized footprint. A rectangular layout is most common, with depth and dimensions depending on the vertical constraints and site geography. Storage options typically will utilize an equalizer or header at the downstream end to drain the system toward the outlet control structure or pump station.

Structural design to accommodate any dead, live and hydrostatic loads should be evaluated for the chosen material options. A concrete vault will act as a rigid box and require heavy reinforcing steel to resist bending moments in the slabs and walls with the standard structural design following ACI 350. As a heavy structure, controlling differential settlement through a competent subgrade foundation also is important.

Structural loading for a large-diameter pipe array is achieved utilizing traditional pipe-backfill interaction, allowing the pipe to act in ring compression with the backfill around it. Lateral support from the backfill is used to transfer loads, so the quality and placement of backfill is important—a class I crushed angular stone or gravel in accordance with ASTM D2321 is recommended for the massive pipe sizes used in a CSO/SSO pipe array. It’s interesting to note that because SRPE incorporates steel reinforcing ribs within the HDPE pipe wall, the structural design follows AASHTO LRFD Sec.12.7 (steel pipe methodology) rather than unreinforced thermoplastic design. Also, if the design will take any future seismic activity concerns into account, a flexible pipe system generally is preferable to a rigid system due to its resiliency and load-distribution geometry.

Corrosion Resistance

As one may imagine, the internal environment of a large sanitary tank can be exceptionally hostile, so resistance to corrosion is important. Microbially induced corrosion (MIC) occurs when anaerobic bacteria in wastewater generate hydrogen sulfide gas (H2S), which converts to sulfuric acid when it meets moisture on the walls above the water line. This acid can damage concrete, so a specialized antimicrobial admixture or internal protective coating should be used. SPRE, HDPE and fiberglass are inherently resistant to MIC and degradation associated with storing sanitary wastewater.

Figure 1. Large-diameter pipe-array installation.

 

Buoyancy

Due to their immense storage volume, underground containment tanks can generate significant buoyant forces if they’re empty and become submerged in groundwater. If the high seasonal groundwater elevation for the selected site is above the invert of the system, then the tank must be checked for flotation. The buoyant uplift force is equal to the area of water displaced multiplied by the unit weight of water (62.4 lb/ft3). The resisting forces include the weight of the tank, the weight of the overburden on top of the tank and any fluid in the tank. A prudent approach is to assume the tank is empty, such as during cleaning. If the resisting forces aren’t enough to overcome the uplift force, then there are options to address this:

  • Add cover or select a tank depth to allow more downward force from the soil column above. For example, if a 120-inch-diameter SRPE pipe has at least 5-foot 5-inch cover, flotation shouldn’t occur with an empty pipe that has groundwater up to the crown. Alternatively, a concrete slab or pavement may be used over the top of the buried tank (such as for a parking area) that can help to offset the uplift force.
  • If cover is too shallow and reducing the rise or diameter isn’t an option, then an anchoring system can be utilized. There are various types of ground anchors (helical ground anchors, load-locking anchors or rock anchors) used with high-capacity straps. Concrete ballast beams also could be used—these are placed on either side of a large-diameter pipe system to engage the backfill columns above.
  • Another option is to utilize a concrete base slab. This slab foundation can be extended around the system’s perimeter to form a shelf or “toe” to engage more backfill.

Installation

  • High-capacity underground concrete wastewater vaults typically are cast-in-place, but in some cases a monolithic system using pre-stressed concrete panels can be used. After site preparation and dewatering (if necessary), the floor base, vertical walls and roof slab are erected through the process of forming, tying rebar, sequential concrete pouring and curing (typically 28 days to reach design strength). Waterproofing or chemically protecting the inside of the tank also may be added. This type of installation takes time and usually requires heavy equipment such as concrete pump trucks, mass earth movers and high-capacity cranes.
  • The installation process for an ultra-large-diameter pipe-array wastewater tank can be expedited using long lightweight pipe sections. Pipe lengths can vary, but 24- to 40-foot-long pieces provide efficiency and fewer joints. Once excavation and pipe bedding are complete, the pipe sections and downstream header are set in place to match the layout drawings. For pipe connections, a field extrusion-welded joint or watertight steel-reinforced bell and spigot joint may be considered. The pipe backfill typically is a class I material per ASTM D2321 (crushed angular material such as No. 57 stone works well). It’s important to place the stone in a balanced fashion, supporting the adjacent barrels as the backfilling process moves along the system. Precise backfilling can be expedited by using a “stone-slinger” or conveyor truck.
 Figure 2. Example of a joint-isolation test rig.

 

Post-Installation Testing

Due to immense size, the post-installation testing of large-capacity subsurface wastewater storage systems can be very difficult. The following are a few methods and some considerations:

  • Visual inspection: Inspectors rely on CCTV and robot crawlers to inspect small-diameter municipal sanitary systems, but as man-entry structures, large-diameter pipe-array systems and tanks may be evaluated firsthand. After installation, a technician can perform a thorough interior inspection to evaluate joints, material defects, cracks, shape, welds, post-installation debris and other criteria.
  • Hydrostatic exfiltration: This test relies on static head pressure by filling the structure to its maximum design level with water and measuring actual fluid loss through time. It provides awareness of leaks that a visual inspection may miss; however, this test can take considerable time to prepare and complete. Per standards such as ACI 350.1, a concrete tank must undergo a saturation period (often 48 to 72 hours) before the actual 24- to 48-hour testing window begins. Other factors such as evaporation and thermal expansion/contraction should be considered to prevent a false-positive leak indication.
Figure 3. An SRPE QuikJoint® air test.

 

In addition to the municipal coordination and time of filling the tank with several hundred thousand or millions of gallons of water, the disposal may also have considerations. If the hydrotest water has picked up any chemical residues, concrete particulates or form release agents, it may require an NPDES permit before releasing into surface waters or fees to discharge into a publicly owned treatment facility.

Figure 4. Spraying inside a large vault. 

 

Finally, the exact location of any leaks present may be very difficult to identify with a hydrostatic leak-down test. Some professional industry services offer acoustic leak detection (hydrophones) or fluorescent tracer dye injections using a diver or submersible remote-operated vehicle employed at specific zones of the tank to try and locate problem spots.

  • Low-pressure air: Air-pressure testing of large tanks can introduce safety and structural risks due to the extreme amount of stored energy. Because air is highly compressible, at these large volumes even a tiny amount of pressure can create immense thrust. For this reason, traditional smaller-diameter air tests such as ASTM F1417 or ASTM C924 would be difficult and dangerous in large sizes. Another option for air testing large-diameter pipe-array systems would be to utilize a joint-isolation test. This process places a mobile test rig inside the pipe to seal and pressurize a narrow section of air on either side of the joint to verify the leakage rate. These test rigs are available from equipment rental suppliers or can be custom fabricated. Recent advancements with SRPE bell and spigot pipe (called QuikJoint®) also allow for a low-pressure air test where a test rig isn’t necessary. This joint design includes two sanitary gaskets and a test port that allows the annulus between them to be subjected to a low-pressure air test.
Figure 5. Vactor truck sludge removal

 

Future Inspection and Maintenance

Both concrete vaults and large-diameter pipe-array systems utilize integrated access risers to allow physical access inside the tank to perform periodic inspections. Properly trained and equipped personnel following OSHA standards can inspect for sediment buildup and provide condition assessment. The concrete structure should include inspection of the wall joints, roof slab, floor slab and supports for signs of structural cracking, chemical attack, spalling or exposed rebar. The pipe-array inspection should include inspection of the pipe joints, manifold and stub connections.

Any accumulated sludge can be removed using vacuum trucks or high-pressure jetting. The vault allows more open movement, but cleaning the floor surface can be more difficult than the cylindrical barrels of a pipe-array, which promote channel-flow toward the outlet.

Quiz Instructions

Click on the button below to start the quiz for this course. Your score will be tabulated while you wait, and you will receive your certificate upon completion if you correctly answer eight or more questions.

Registration on v1-education.com is required to access the quiz. Use the "Sign Up" link in the top right of v1-education.com to register. If you are already registered simply enter your credentials to access the quiz.

TAKE QUIZ

Continuing Education

The Professional Development Series is a unique opportunity to earn continuing education credit by reading specially focused, sponsored articles in Informed Infrastructure.

If you read the following article, display your understanding of the stated learning objectives, and follow the simple instructions, you can fulfill a portion of your continuing education requirements at no cost to you. This article also is available online at v1-education.com.

Learning Objectives

Upon completion of this article, the reader should be able to:

  • Gain basic design strategies for large-volume subsurface containment of sanitary and combined sewer overflows, spent airfield deicing fluid, aqueous film-forming foam fire-suppression runoff, and industrial wastewater.
  • Review general aspects such as tank sizing, layout, materials, structural loads, buoyancy, durability, installation, and future inspection and maintenance.
  • Discover methods for post-installation testing of ultra-large underground wastewater containment tanks.
  • Identify appropriate methods for evaluating buoyancy, corrosion resistance and post-installation watertightness in large-volume underground wastewater containment systems.

Quiz Instructions

Click on the button below to start the quiz for this course. Your score will be tabulated while you wait, and you will receive your certificate upon completion if you correctly answer eight or more questions.

Registration on v1-education.com is required to access the quiz. Use the "Sign Up" link in the top right of v1-education.com to register. If you are already registered simply enter your credentials to access the quiz.

TAKE QUIZ