US 85 Realignment

Torrington, Wyoming

Retaining Wall

Owner:

Wyoming Department of Transportation

Engineer:

Wyoming Department of Transportation

Contractor:

Reiman Corporation and Miller Walls

Installation:

October 2012

Technical Description:

• Product: Keystone Compac II
• Area: 24,000 sq ft

A town of 7,000 residents, Torrington, Wyoming has found itself surrounded and bisected by trains for nearly 30 years. The BNSF railroad runs through the middle of the town, resulting in no less than five public at-grade crossings throughout town. One of the most heavily trafficked crossings is that of US 85. In order to travel south on US 85, motorists must first cross the railroad tracks. In order to cross the tracks, drivers must deal with the normal flow of traffic combined with the additional car traffic from commuters at Holly Sugar (a major employer for the area) and heavy train traffic; resulting in the perfect recipe for congestion.

The realignment of US 85 in Torrington is a project 30 years in the making. Mike Varney, Mayor of Torrington, said (in a television interview with local station KOTA) that the City first began discussing plans to separate the railroad crossing from US 85 in 1979. According to BNSF, in 2005 the US 85 crossing was closed over three hours per day due to train traffic. Estimates predicted trains would close the crossing by as much as five hours per day by 2025.

It was not until late October 2012 when efforts to realign where US Highway 85 enters Torrington, Wyoming finally began. Prior to construction, travelers along US 85 were met with a stop light just two car lengths ahead of the railroad tracks. A major undertaking, the realignment significantly reduced the town’s train traffic congestion, improved safety on the roads and drastically changed the look of Torrington.

A main component to the realignment was a 24,000 square foot Keystone Compac II retaining wall. Every construction step necessary for completing the realignment relied, in some way, upon the construction of this wall. “The bridge couldn’t be completed until the wall reached a certain height; road construction couldn’t take place until the wall was done. The wall was important to the whole project,” said Tom Miller of Miller Walls. The retaining wall was constructed around pre-driven bridge pylons, allowing the crew from Reiman Corp, the jobs general contractor, to work on the bridge while the wall installation took place.

“We had to get under the bridge in some places to install wall units,” explained Miller. “With the wall being one sided, and the dirt crew needing to bring a large volume of material on-site, space was limited.” Wall installers worked in unison with the dirt crew to ensure the retained material was built to the same height as the wall. Native materials were not used for the walls backfill. Instead, well graded crushed base was trucked in from an off-site manufacturer. “We had trucks driving right behind the wall, near the grid,” added Miller.

The installation crew overcame more than just tight work space in order to complete the job. “We had a nasty winter,” pointed out Miller. “We faced a lot of cold weather and frost. The crew raced against Mother Nature to build the wall to a height that allowed bridge structures to be poured so work could continue through the winter.” Reaching heights of 31 feet in some places, crews installed geogrid every three courses, on average, throughout the entire height of the wall. The use of grid provided the necessary reinforcement to ensure the retaining wall structure remained stable as the height of the wall increased.

Those passing through Torrington will never see the grid within the wall. Instead, they will see birds, a design element added by the project’s landscape architect. Each bird uses full-sized Keystone Compac units in a color different from the rest of the wall. “Not only did we have to keep the materials separate, we had to stack the units for the birds as we built the wall,” says Miller. “We had a guy on the ground who would coordinate with the guy laying the block. The exact station and elevation of each colored unit had to be noted so we could be sure that when installation was completed, it actually looked like birds.”

Construction on the realignment is ongoing, though installation on the wall was completed in early April 2013. When complete in spring 2014, US 85 will enter the town over the existing UPRR/BNSF mainline railroad tracks, as well as US 26.

Technical Description:

• Product: Keystone Compac II
• Area: 24,000 sq ft