Scott Creek Trunk Sewer, Phase II

Belmont, Michigan
Sanitary Sewer
Owner:
Plainfield Charter Township
Engineer:
Prein & Newhof
Contractor:
Kamminga & Roedvoets
Technical Description:
  • 2,000 LF of 15-in. Gasketed PVC TRUSS PIPE®
Installation:
October 2013

In the second phase of extensive wastewater system upgrades in Plainfield Charter Township, Michigan, five pump stations needed to be either rehabilitated or replaced. In addition to the pump station upgrades, the Scott Creek Trunk Sewer was to be replaced or rehabilitated from West River Drive to Pine Island Drive. Plainfield Charter Township is a large and growing community just north of Grand Rapids, Michigan. It was imperative that these improvements be done quickly and efficiently to provide as little disruption to the surrounding community as possible.

 

The existing trunk sewer line was a reinforced concrete pipe line with an increasing amount of infiltration and some sags in the pipe. The original US-131 crossing also had significant pipe sag in it causing velocities below design conditions that required it be replaced. A trunk sewer serves as the main artery for the wastewater collection system, and it is imperative for the entire system that the trunk line be able to collect and convey wastewater from numerous main sewer lines to a water quality treatment center without fail. Plainfield Charter Township used Contech Engineered Solutions’ Gasketed PVC –TRUSS PIPE® for this replacement. TRUSS PIPE provides a unique, semi-rigid wall design and unparalleled in-ground performance. Given that TRUSS PIPE can withstand heights of cover greater than 40 feet yet also provide H-20 live loading with less than one feet of cover, Plainfield was reassured that this was the optimal solution and product for their particular project and site constraints. Not only that, but the newly installed TRUSS PIPE provided a glossy smooth interior with a Manning’s “n” value of 0.009 that would reduce internal flow resistance and provide the hydraulic velocities required by the original design conditions.

The most significant element of this project was the crossing under US-131 north of Grand Rapids. Each bore was completed from the wide median and were each approximately 160 feet. The dewatering process for the bores was a concern for Michigan Department of Transportation (MDOT) due to the length and depth, this required groundwater level monitoring. The polymer manhole in the median was 19.1’ deep, and cover over TRUSS PIPE at the deepest end of the casing was approximately 23 feet.

The project was a success in that the crossing was completed on grade with no settlement to the US-131 pavement. Rick Solle, Plainfield Charter Township Engineer commented, “The Scott Creek Trunk crossing under US-131 was a success story for all parties involved: the Township, the Contractor and MDOT. MDOT had apprehension at the beginning of the project and required monitoring throughout the project of both the pavement elevation and the groundwater levels. The cooperation between the Owner, Contractor and MDOT throughout this process made a difficult project a huge success!”

Solle added, “Contech’s Truss Pipe offers us a premium sanitary sewer product to address all the concerns with deep interceptor installations. The pipe strength, joint quality, the characteristics of PVC virtually eliminate all the long-term issues found with pipe options historically used in these applications”

 

 

800-338-1122 | www.ContechES.com
© 2017 Contech Engineered Solutions LLC